Rosengarten: city executive asks parliament again to close the motion on redesigning the route
For the second time, the city executive is asking the city parliament to close an urgent motion on relieving the Bucheggstrasse/Rosengartenstrasse/Hardbrücke route. It has scaled back public consultation because of the cut to the 2026 budget.
The urgent motion (Dringliche Motion, GR No. 2020/63) by the SP, Greens, GLP, AL and EVP requires the city executive (Stadtrat) to put a spending proposal to the city parliament (Gemeinderat) that clearly reduces traffic on the Bucheggstrasse/Rosengartenstrasse/Hardbrücke route and redesigns it to suit the city, with a broad public debate. A motion is binding; the executive can only ask parliament to close it with a report. Its first request failed: on 19 November 2025 parliament took note of the report but gave the executive another twelve months.
What the city executive reports now
According to the proposal (Weisung), the executive supports the aims but considers a single spending proposal for everything neither feasible nor sensible. It is pursuing several projects in parallel (see also the appeal on the crossings):
| Project | Status |
|---|---|
| Two street-level crossings (Lehenstrasse, Wibichstrasse), two bus priority points | refused by the cantonal government on 23 September 2026; appeal at the administrative court |
| 30 km/h limit | city's appeal rejected on 23 September 2026, not taken further; remains the goal |
| Measures accompanying the widening of the northern motorway bypass (Nordumfahrung) | around 30 measures; stage 1 by early 2028, stage 2 expected by 2031; framework credit to follow separately |
| New planning process | internal expert planning with four workshops, one held before the summer holidays |
Less public involvement
The "Zukunft Rosengarten" dialogue process had to be changed after parliament cut the 2026 budget. Public dialogue events cannot take place in 2026/27 as planned; later participation depends on the budget.
According to the proposal, more than 50,000 motor vehicles a day use the route, while a two-lane city main street carries at most 20,000–25,000. The accompanying measures will not reduce traffic that far either. The executive believes another single major project would be "doomed to fail again", as in 2010 and 2020.